  • Site 11 has an increase in units from 23 to 25, construction permit has been filed and is pending.
  • Site 13 has building permit approved as of Sept 11 2026.
  • new total unit count for phase 1 is 370.

Image 1: South side of promenade | Image 2: North side of promenade
55286403552_8b11461fde_c.jpg
55287729205_3f0ecee3dd_c.jpg


  1. Alston Properties with 1X1 Architecture
    Site 11 | 64 Israel Asper Way, 25 Units, 2 CRU, 6L 2024-11-12-Development Permit
    Site 13 | 44 Israel Asper Way, 35 Units, 1 CRU, 6L 2024-11-12-Development Permit

  2. Burrows with 2 Architecture
    Site 08 | 80 Israel Asper Way, 16 Units, 0 CRU, 4L 2026-01-15-Construct New Building Permit U/C
    Site 10 | 68 Israel Asper Way, 06 Units, 1 CRU, 4L 2026-01-15-Construct New Building Permit U/C
    Site 12 | 50 Israel Asper Way, 46 Units, 8 CRU, 6L 2026-05-12-Construct New Building Permit U/C

    [*]Santa Fe Developments with ATLRG Architecture
    Site 16 | 26 Israel Asper Way, 33 Units, 2 CRU, 6L 2026-04-07-Construct New Building Permit U/C

    [*]StreetSide Developments with Prairie Architects
    Site 15 | 32 Israel Asper Way, 45 Units, 2 CRU, 6L 2026-03-25-Development Permit

    [*]Vishin Developments and TradeMark Homes with ATLRG Architecture
    Site 14 | 00 Israel Asper Way, 00 Units, 0 CRU, 4L - Unconfirmed

    [*]Forks Renewal Corporation with Number Ten
    Site 09 | 72 Israel Asper Way, 91 Units, 4 CRU, 6L 2026-02-12-Construct New Building Permit U/C

    [*]University of Winnipeg Community Renewal Corporation 2.0 with LM Architectural Group
    Site 07 | 00 Israel Asper Way, 73 Units, 1 CRU, 7L

    Total: 370 Units, 21 CRU, 55L
 
High level,

Alston plans to build one site at a time, start with 13 then move onto site 11.
The original development team for site 14 fell apart.
Site 7 developed by UWRC, may start after other priority projects break ground (Market Lands, Granite Riverside).
The condo building at site 15 will most likely be one of the last to get going.
Thanks for the info! I wonder if we get a full redesign for site 14?
 