  #221  
Old Posted Sep 8, 2019, 1:07 AM
Rhome's Avatar
Rhome Rhome is offline
Registered User
 
Join Date: Mar 2007
Posts: 80
Since the Decision to approve the project--issued Sept. 8, 2016--has a 3-year expiration date, and given the timing of these latest permits so close to the 3-year deadline, sounds like the developer is just trying to keep the project alive so that they don't have to seek a new land use review.

From the Approval:

Expiration of this approval. An approval expires three years from the date the final decision is rendered unless a building permit has been issued, or the approved activity has begun. Where a site has received approval for multiple developments, and a building permit is not issued for all of the approved development within three years of the date of the final decision, a new land use review will be required before a permit will be issued for the remaining development, subject to the Zoning Code in effect at that time.

Last edited by Rhome; Aug 6, 2022 at 3:29 AM.
Reply With Quote
     
     
  #222  
Old Posted Sep 9, 2019, 8:02 PM
RED_PDXer RED_PDXer is offline
Registered User
 
Join Date: Dec 2007
Location: Portland, OR
Posts: 793
Quote:
Originally Posted by Rhome View Post
Since the Decision to approve the project--issued Sept. 8, 2016--has a 3-year expiration date, and given the timing of these latest permits so close to the 3-year deadline, sounds like the developer is just trying to keep to project alive so that they don't have to seek a new land use review.

From the Approval:

Expiration of this approval. An approval expires three years from the date the final decision is rendered unless a building permit has been issued, or the approved activity has begun. Where a site has received approval for multiple developments, and a building permit is not issued for all of the approved development within three years of the date of the final decision, a new land use review will be required before a permit will be issued for the remaining development, subject to the Zoning Code in effect at that time.
For the permit to be issued, wouldn't the developer have to fork over an immense amount of cash? It would be millions of dollars given the number of units, SDCs, permit fees, 1% surcharge for affordable housing, etc.
Reply With Quote
     
     
  #223  
Old Posted Oct 11, 2019, 6:15 PM
pdxsg34 pdxsg34 is offline
Registered User
 
Join Date: Dec 2017
Posts: 314
The Lloyd parking lot redevelopment by the theater is cancelled...

via PortlandMaps:
Quote:
10/10/19 - commercial building project canceled, per BDS Process Management. See attached letter. Closing public works permit, as conditions no longer apply.
This only adds to my speculation that Lloyd might be considering the ballpark, but could mean anything. Either way, what a cluster.
Reply With Quote
     
     
  #224  
Old Posted Oct 11, 2019, 11:04 PM
NOPO NOPO is offline
Registered User
 
Join Date: Sep 2019
Posts: 139
I am still hopeful for this land. It’s crying for good mid to high rise mixed use development.
Reply With Quote
     
     
  #225  
Old Posted Oct 12, 2019, 6:21 AM
urbanlife's Avatar
urbanlife urbanlife is offline
A before E
 
Join Date: Aug 2001
Location: Milwaukie, Oregon
Posts: 11,752
Quote:
Originally Posted by pdxsg34 View Post
The Lloyd parking lot redevelopment by the theater is cancelled...

via PortlandMaps:

This only adds to my speculation that Lloyd might be considering the ballpark, but could mean anything. Either way, what a cluster.
This is my suspicion as well, if PBP has been talking to them about the Lloyd Center as a possible location, the PBP wouldn't want any new projects to be going up on a site they would want to redevelop around a baseball stadium.

I personally really hope this happens because a baseball stadium would work in the Lloyd District and Terminal 2 would make a better urban housing expansion that could easily be a dense mixed income development. Plus it would be easy to expand the streetcar to this area rather than the light rail.


Quote:
Originally Posted by NOPO View Post
I am still hopeful for this land. It’s crying for good mid to high rise mixed use development.
Keep in mind, the size of a MLB stadium is about half the size of the site that the Lloyd Center sits on, so the other half of the site would be prime for a commercial center and housing development that could easily lead to being a number of high rises and lots of mixed use developments.
Reply With Quote
     
     
  #226  
Old Posted Oct 12, 2019, 6:40 AM
NOPO NOPO is offline
Registered User
 
Join Date: Sep 2019
Posts: 139
Quote:
Originally Posted by urbanlife View Post
Keep in mind, the size of a MLB stadium is about half the size of the site that the Lloyd Center sits on, so the other half of the site would be prime for a commercial center and housing development that could easily lead to being a number of high rises and lots of mixed use developments.
This would be amazing. I hope there’s genuine consideration happening to make this a reality.
Reply With Quote
     
     
  #227  
Old Posted Dec 4, 2019, 4:50 PM
MarkDaMan's Avatar
MarkDaMan MarkDaMan is offline
Moderator
 
Join Date: May 2005
Location: Portland
Posts: 7,508
https://www.oregonlive.com/business/...6-million.html

Quote:
Lender pulls plug on major Lloyd District redevelopment, demands $36 million
Today 6:30 AM
By Jeff Manning | The Oregonian/OregonLive

In another sign that Portland’s long real estate and construction boom is slowing, an ambitious plan to build more than 1,100 apartment units in the Lloyd District has quietly died.

The lender to the project known as 1400 Multnomah pulled the plug in late October claiming that developers Bob Bisno and Dan Palmer’s operating company had stopped making payments on their loan.

“Borrower is in default and appears to be insolvent,” the lender claimed in a lawsuit filed in October. “The real property, plaintiff’s collateral, is adrift.”

The suit alleges that the Santa Monica-based developers blew through $31 million and never got a single apartment built.

Few predicted this kind of disaster when Bisno and Palmer first came to town in 2016. Oregon had boasted some of the best job growth in the country, which fueled a surge of new arrivals and a housing shortage. An unprecedented explosion of high-end apartment construction followed, reshaping Portland’s skyline.
...(continues)
__________________
make paradise, tear up a parking lot
Reply With Quote
     
     
  #228  
Old Posted Dec 4, 2019, 5:03 PM
johnliu johnliu is offline
Registered User
 
Join Date: Jul 2017
Posts: 197
"In 2011, only 445 new apartments came to market in the entire Portland Metro area. Three years later, the number had jumped nearly ten-fold to 4,367, according to the CoStar Group, a leading provider of real estate data and analytics. The frenzy peaked in 2018, when the number of new apartments reached 6,059. This year will not be far behind.

In all, more than 31,000 new apartment units were built in the Portland metro area over the last six years.

Until now, there’s been sufficient demand in the market to absorb the flood of new rentals. That may be changing, said Mark Barry, who for years has published a newsletter tracking the Portland apartment market. He pointed to predictions that the supply of new units will exceed demand for the next two years.

“We’ve never seen this kind of boom before,” he said. “Anybody betting against the Portland market has been wrong. But inevitably the pendulum is going to begin swinging back.” "
Reply With Quote
     
     
  #229  
Old Posted Dec 4, 2019, 5:26 PM
Eco_jt's Avatar
Eco_jt Eco_jt is offline
Registered User
 
Join Date: Aug 2009
Location: Portland
Posts: 114
One of the commenters in the article posted:

CoStar is off, in the business and in the 4 county METRO new apts:
2011 - 1075
2012 -2273
2013 -7535
2014 - 6863
2015 - 6461
2016 - 14883
2017 - 9820
2018 - 24652

I may be 10%-15% high (like the Lloyd Center properties that look dead) since these are the properties announced, but CoStar is low.

BTW - There are enough developers that someone may come in and steal the project.
Reply With Quote
     
     
  #230  
Old Posted Dec 4, 2019, 6:48 PM
marlonwarren's Avatar
marlonwarren marlonwarren is offline
Registered User
 
Join Date: Nov 2008
Posts: 60
Red face Questionable pre-design presentation . . . .

When I first saw the renderings for this project back in 2016, my first thought was, are these people serious! This project looks like "Cookie Cutter" Soviet Style Apartment Designs . . .

No surprise at the outcome . . . Portland deserves BETTER!
Reply With Quote
     
     
  #231  
Old Posted Dec 4, 2019, 7:52 PM
maccoinnich maccoinnich is offline
Moderator
 
Join Date: Jan 2009
Location: Portland
Posts: 7,389
Quote:
Originally Posted by Eco_jt View Post
BTW - There are enough developers that someone may come in and steal the project.
Design review approvals are good for three years, which has now passed. At a minimum they'd need a new design review application.
__________________
"Maybe to an architect, they might look suspicious, but to me, they just look like rocks"

www.twitter.com/maccoinnich
Reply With Quote
     
     
  #232  
Old Posted Dec 5, 2019, 12:05 AM
PdX Farr PdX Farr is offline
RCTID
 
Join Date: Apr 2016
Location: Portland
Posts: 62
Batter up?
Reply With Quote
     
     
  #233  
Old Posted Dec 6, 2019, 12:30 AM
urbanlife's Avatar
urbanlife urbanlife is offline
A before E
 
Join Date: Aug 2001
Location: Milwaukie, Oregon
Posts: 11,752
What I want to know is what did the company do with $31 million, that is a lot of money to blow through without breaking ground on a project. I hope this means the architecture firm got paid top dollar for their design work.
Reply With Quote
     
     
  #234  
Old Posted Dec 6, 2019, 9:35 PM
marlonwarren's Avatar
marlonwarren marlonwarren is offline
Registered User
 
Join Date: Nov 2008
Posts: 60
Portland is Not their only problem . . .

A simple Goggle search, tells you all you need to KNOW. These Con Men have done the same thing in California . . . .

https://www.pressdemocrat.com/news/7...rtment?sba=AAS
Reply With Quote
     
     
  #235  
Old Posted Dec 6, 2019, 9:41 PM
RED_PDXer RED_PDXer is offline
Registered User
 
Join Date: Dec 2007
Location: Portland, OR
Posts: 793
Quote:
Originally Posted by urbanlife View Post
What I want to know is what did the company do with $31 million, that is a lot of money to blow through without breaking ground on a project. I hope this means the architecture firm got paid top dollar for their design work.
They bought the 5-acre property for about $22 million according to the Oregonian story. They spent $9 million on other things like design and land use approvals.
Reply With Quote
     
     
  #236  
Old Posted Dec 8, 2019, 7:52 AM
urbanlife's Avatar
urbanlife urbanlife is offline
A before E
 
Join Date: Aug 2001
Location: Milwaukie, Oregon
Posts: 11,752
Quote:
Originally Posted by RED_PDXer View Post
They bought the 5-acre property for about $22 million according to the Oregonian story. They spent $9 million on other things like design and land use approvals.
That makes sense, I didn't know they spent that much money on the site.
Reply With Quote
     
     
  #237  
Old Posted Jan 11, 2021, 11:31 PM
MarkDaMan's Avatar
MarkDaMan MarkDaMan is offline
Moderator
 
Join Date: May 2005
Location: Portland
Posts: 7,508
Looks like they're going to break up the superblock.

__________________
make paradise, tear up a parking lot
Reply With Quote
     
     
  #238  
Old Posted Jun 27, 2022, 12:14 AM
maccoinnich maccoinnich is offline
Moderator
 
Join Date: Jan 2009
Location: Portland
Posts: 7,389
Ownership of this site transferred to Mosaic Real Estate Investors in May
__________________
"Maybe to an architect, they might look suspicious, but to me, they just look like rocks"

www.twitter.com/maccoinnich
Reply With Quote
     
     
  #239  
Old Posted Aug 3, 2022, 2:21 PM
PhillyPDX PhillyPDX is offline
Registered User
 
Join Date: Aug 2022
Posts: 358
There have been active test borings on this lot over the last week. Makes me think the new owners mentioned are up to something.
Reply With Quote
     
     
End
 
 
Reply

Go Back   SkyscraperPage Forum > Regional Sections > United States > Pacific West > Portland > Downtown & City of Portland
Forum Jump


Thread Tools
Display Modes

Forum Jump


All times are GMT. The time now is 8:15 AM.

     
SkyscraperPage.com - Archive - Privacy Statement - Top

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.