Quote:
Originally Posted by SamInTheLoop
See. Steely, this confirms the project is probably around 2-3 months behind schedule (which I estimated a couple weeks ago). And it is actually quite prudent to continue to question this project and developer, because until full construction financing is arranged, the project is not on sound financial footing. This is a great project and I hope it does not run into deep troubles. But that does not mean we should give the developers a pass when it comes to their troubles and just look the other way. Rome was also not built on blind faith...
|
I also mentioned somewhere on this forum that I was told June, so there...
Just because they haven't informed us of there financing, doesn't mean they don't have it.
You guys are beginning to sound like D. Roeder and the rest of the media in criticising financing on the Spire.
Found my previous post from September 13, 2006:
http://forum.skyscraperpage.com/show...=41986&page=72
That's exactly what it's for.
I've asked a few questions of my contact, and this it what I've found out. Remember this information is subject to change...
I was wondering how far down the excavation of the area outside the core would be going down?
Generally, 8' above the lowest point in the core excavation (b/c there is no mat around the perimeter)
I was also wondering when do you believe the tower crane will be erected?
As soon as the mat is poured. We plan on pouring in ~3 weeks.
Finally, I asked this question before, but need a but of clarification. About when will the building be up to Wacker Drive and start to rise?
The core should be up to grade around the end of November. The perimeter should be up to Wacker around June 07.