2006/07/05 (news from the developper's site)
At present, the Construction Project Jasper Tower is in progress and on schedule. The details of the construction are as follows:
The reinforced concrete core tube of the main building has been built to 21F;
The core-tube periphery steel structure of the main building has been built to 16F;
The steel frame carrier plate of the main building has been built to 13F;
The lightweight sand block structure of the basement has been completed 95%. The construction of grooving for pipelines has started as well;
The embedded parts of the main building glazing wall have been conveyed to the spot in batches; wielding and anti-pullout experiment has also been conducted; some parts have been embedded too.
The year of 2006 is a structure year for the Construction Project Jasper Tower. Its major target is to make sure that the construction structure will have been sealed by the end of this year. When the main structure is under construction in accordance with the prearrangement.
...
It no doubt that the design and the construction quality of the Jasper Tower curtain wall has great influence on the overall quality of the Construction Project Jasper Tower, the upgrade of the whole construction and the integral embodiment of the original intention of the design. So the design and construction of the Jasper Tower curtain wall is enormously difficult and complex with a view of embodiment of the perfect blue print. To ensure a smooth construction of the curtain wall, a good many detailed projects are needed to guide the further design and construction for the next step during the period from May to August. The project department will cooperate with the curtain wall contractor, the design institute and spot management department, reasonably arrange the schedule, figure out the specifics and solve the problems found in the curtain wall construction item by item with the spirit of ants gnawing at a bone, so as to make sure that the further design of the curtain wall will be completed earlier and then can enter into a substantial construction phase.