Quote:
Originally Posted by Biff
The boom of the crane is within 20 ft of the top of the concrete pump. They need to raise the core (and form unit) at least one more level to get the required 3 more levels of hollowcore installed. Right now, only 2 more levels are able to be installed due to the form unit. Once the 3rd level (or 12th floor) is in place and grouted, they can anchor the crane to the 12th floor. From there the crane can be raised, the concrete pump can be reinstalled and the core and the building can continue to rise as usual.
|
Thanks for the clarity Biff. I'm sure there were a number of people wringing their hands, either in trepidation or in glee, at the thoughts that something might be wrong with this project.