HomeDiagramsDatabaseMapsForum About
     

Go Back   SkyscraperPage Forum > Global Projects & Construction > Supertall Construction


    Waldorf Astoria Hotel & Residences Miami in the SkyscraperPage Database

Building Data Page   • Comparison Diagram   • Miami Skyscraper Diagram

Map Location

Reply

 
Thread Tools Display Modes
     
     
  #441  
Old Posted May 2, 2024, 6:14 PM
UrbanImpact's Avatar
UrbanImpact UrbanImpact is offline
Registered User
 
Join Date: Jul 2002
Location: Fort Lauderdale, FL
Posts: 1,388
Quote:
Originally Posted by wpolom View Post
Well, we don't want to end up with a tilting skyscraper like in New York, and San Francisco.
Yup, No tilting and only cantilevering! I would guestimate sometime in end of 2026 or early 2027 for topping off.
Reply With Quote
     
     
  #442  
Old Posted May 2, 2024, 6:42 PM
lio45 lio45 is offline
Moderator
 
Join Date: Aug 2007
Location: Quebec
Posts: 42,344
Impressive! Are those bunches of rods going to turn into columns, for underground parking stories?

Edit -- I hadn't looked at the pics before posting, clearly not, they're just all way too close. A full slab is going to be poured at that level, I assume?
__________________
Suburbia is the worst capital sin / La soberbia es considerado el original y más serio de los pecados capitales
Reply With Quote
     
     
  #443  
Old Posted May 2, 2024, 9:02 PM
BrickellBased BrickellBased is offline
Registered User
 
Join Date: Apr 2023
Location: Miami, FL
Posts: 203
Yeah - they'll be connected via a mat pour that will distribute the weight of the building more evenly across them.

I would think the mat pour should be somewhat soon - within a few months. They have a lot of rebar to lay for that. Then vertical construction will start.

These big towers in Miami clearly require much deeper and larger foundations per height than buildings up north. Okan and Panorama towers had similar mat pour sizes to Petronas Towers and this will probably be the similar - although I think this required more piling work.

Quote:
Originally Posted by lio45 View Post
Impressive! Are those bunches of rods going to turn into columns, for underground parking stories?

Edit -- I hadn't looked at the pics before posting, clearly not, they're just all way too close. A full slab is going to be poured at that level, I assume?
Reply With Quote
     
     
  #444  
Old Posted May 4, 2024, 2:32 AM
Altoic's Avatar
Altoic Altoic is offline
Registered User
 
Join Date: Nov 2020
Location: Florida
Posts: 1,267
Reply With Quote
     
     
End
 
 
Reply

Go Back   SkyscraperPage Forum > Global Projects & Construction > Supertall Construction
Forum Jump



Forum Jump


All times are GMT. The time now is 8:02 AM.

     
SkyscraperPage.com - Archive - Privacy Statement - Top

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.