Old Posted Apr 2, 2019, 8:54 PM
bomberjet bomberjet is offline
Registered User
 
Join Date: Nov 2012
Location: Winnipeg
Posts: 13,785
It'll be quite an effort to remove the temporary shoring works. Which from my understanding is everything they installed on site. It will be difficult.
Reply With Quote
     
     
  #3142  
Old Posted Apr 2, 2019, 9:10 PM
Stormer's Avatar
Stormer Stormer is offline
Registered User
 
Join Date: Jan 2008
Posts: 7,235
Quote:
Originally Posted by bomberjet View Post
It'll be quite an effort to remove the temporary shoring works. Which from my understanding is everything they installed on site. It will be difficult.
I don't know why you would bother. You are liable to cause a collapse. Why not just leave the shoring in place?
Reply With Quote
     
     
  #3143  
Old Posted Apr 2, 2019, 11:20 PM
pappcam pappcam is offline
Registered User
 
Join Date: Mar 2008
Location: Regina
Posts: 608
Quote:
Originally Posted by Stormer View Post
I don't know why you would bother. You are liable to cause a collapse. Why not just leave the shoring in place?
Are they allowed to do that?
Reply With Quote
     
     
  #3144  
Old Posted Apr 3, 2019, 12:26 AM
one_brick_at_a_time's Avatar
one_brick_at_a_time one_brick_at_a_time is offline
Registered User
 
Join Date: Apr 2009
Location: Regina/Toronto
Posts: 2,245
They would leave the shoring in place. That way future developers would have an easier time building.
Reply With Quote
     
     
  #3145  
Old Posted Apr 3, 2019, 12:45 AM
pappcam pappcam is offline
Registered User
 
Join Date: Mar 2008
Location: Regina
Posts: 608
Quote:
Originally Posted by one_brick_at_a_time View Post
They would leave the shoring in place. That way future developers would have an easier time building.
Does a surface parking lot need all that shoring? How about a 2 story office building?

I don't see any big projects happening in Regina for quite a while.
Reply With Quote
     
     
  #3146  
Old Posted Apr 19, 2019, 6:05 PM
StealthGirl's Avatar
StealthGirl StealthGirl is offline
Registered User
 
Join Date: Jun 2008
Posts: 1,222
Capital Pointe is up for sale for $8.5M.

https://regina.ctvnews.ca/capital-po...rket-1.4387139
Reply With Quote
     
     
  #3147  
Old Posted Apr 20, 2019, 1:46 AM
scotty c scotty c is offline
Registered User
 
Join Date: Nov 2012
Posts: 204
Do you think the City holds off on filling in the hole in hopes of a quick sale? Would seem that having a lot of the excavation work done already may be a selling feature of the lot.
Reply With Quote
     
     
  #3148  
Old Posted Apr 20, 2019, 2:35 AM
BrutallyDishonest2 BrutallyDishonest2 is offline
Registered User
 
Join Date: Apr 2015
Posts: 1,426
Quote:
Originally Posted by scotty c View Post
Do you think the City holds off on filling in the hole in hopes of a quick sale? Would seem that having a lot of the excavation work done already may be a selling feature of the lot.
According the the city it's a safety issue, so presumably they will continue as they are.

Additionally, any sale that did happen would be a lengthy process as its through the courts.
Reply With Quote
     
     
  #3149  
Old Posted May 7, 2019, 11:01 PM
StealthGirl's Avatar
StealthGirl StealthGirl is offline
Registered User
 
Join Date: Jun 2008
Posts: 1,222
Winning tender to fill the hole should be announced within days.
Fill to start in summer and finish in early fall.

https://www.cjme.com/2019/05/07/514507/
Reply With Quote
     
     
  #3150  
Old Posted May 7, 2019, 11:18 PM
pappcam pappcam is offline
Registered User
 
Join Date: Mar 2008
Location: Regina
Posts: 608
This should be marked as a cancelled project, no?
Reply With Quote
     
     
  #3151  
Old Posted May 8, 2019, 1:24 PM
HomeInMyShoes's Avatar
HomeInMyShoes HomeInMyShoes is offline
arf
 
Join Date: May 2005
Location: File 13
Posts: 13,984
Quote:
Originally Posted by pappcam View Post
This should be marked as a cancelled project, no?
Is litigated a project status? Yes, the moderators should mark this as cancelled.
__________________

-- “We heal each other with kindness, gentleness and respect.” -- Richard Wagamese
-- “Unless someone like you cares a whole awful lot, Nothing is going to get better. It's not.” -- Dr. Seuss
Reply With Quote
     
     
  #3152  
Old Posted May 8, 2019, 2:53 PM
bomberjet bomberjet is offline
Registered User
 
Join Date: Nov 2012
Location: Winnipeg
Posts: 13,785
I thought the tender said remove all shoring works? I'm not sure another developer would take on the risk of something like that. Partially installed shoring for a failed development 5 stories below ground. Maybe though.
Reply With Quote
     
     
  #3153  
Old Posted May 9, 2019, 12:39 AM
StealthGirl's Avatar
StealthGirl StealthGirl is offline
Registered User
 
Join Date: Jun 2008
Posts: 1,222
Yes, shoring is to be removed. I was surprised to see fixing sidewalks included, but I'm glad that was included.

Reply With Quote
     
     
  #3154  
Old Posted May 9, 2019, 2:09 AM
mitchellk12's Avatar
mitchellk12 mitchellk12 is offline
Moderator
 
Join Date: Sep 2015
Location: Saskatoon, SK
Posts: 652
Quote:
Originally Posted by HomeInMyShoes View Post
Is litigated a project status? Yes, the moderators should mark this as cancelled.
Done
Reply With Quote
     
     
  #3155  
Old Posted May 9, 2019, 1:13 PM
HomeInMyShoes's Avatar
HomeInMyShoes HomeInMyShoes is offline
arf
 
Join Date: May 2005
Location: File 13
Posts: 13,984
Thanks mitchellk12.
__________________

-- “We heal each other with kindness, gentleness and respect.” -- Richard Wagamese
-- “Unless someone like you cares a whole awful lot, Nothing is going to get better. It's not.” -- Dr. Seuss
Reply With Quote
     
     
  #3156  
Old Posted May 27, 2019, 11:54 PM
StealthGirl's Avatar
StealthGirl StealthGirl is offline
Registered User
 
Join Date: Jun 2008
Posts: 1,222
Work to fill the hole has been contracted out officially.

Quote:
The work is expected to cost $2,601,819, excluding taxes. The city is also allowing for a contingency of $390,272. The total cost of $2,992,091 will be charged to the property tax bill of the owner, which land titles show is still Westgate Properties.

Construction will start in June, according to an administration report that came to council on Monday. It is expected to be complete by the end of October.

...he said crews from the successful bidder, CBS Contracting Inc., will sometimes work 24 hours a day. Work will be scheduled to avoid traffic disruptions, according to administration.

...In the end, the property will be fenced off and paved over with asphalt.
https://leaderpost.com/news/saskatch...e-hole-in-june
Reply With Quote
     
     
  #3157  
Old Posted May 28, 2019, 1:38 AM
roryn1 roryn1 is offline
Registered User
 
Join Date: Jun 2016
Posts: 1,028
drove by this today and there's a Cushman and Wakefield For Sale sign on it now
Reply With Quote
     
     
  #3158  
Old Posted Jun 6, 2019, 12:32 PM
one_brick_at_a_time's Avatar
one_brick_at_a_time one_brick_at_a_time is offline
Registered User
 
Join Date: Apr 2009
Location: Regina/Toronto
Posts: 2,245
With millions at stake, creditors pitch hotel on Capital Pointe site

https://leaderpost.com/news/local-ne...al-pointe-site
Reply With Quote
     
     
  #3159  
Old Posted Jun 6, 2019, 1:34 PM
prairieguy prairieguy is offline
Registered User
 
Join Date: Apr 2007
Posts: 1,488
Sounds like the city is acting responsibly here. Hope they stick to their guns.
Reply With Quote
     
     
  #3160  
Old Posted Jun 6, 2019, 1:59 PM
roryn1 roryn1 is offline
Registered User
 
Join Date: Jun 2016
Posts: 1,028
"He said he’s not yet sure how much that will cost, but is confident his company can finance it. It might include a plan to buy out the bank that owns the first ranked mortgage on the property. His team would convert their debt to equity and find a “local credible partner” to build. According to Nichilo, there’s already interest."

Yea... this sounds terrible lol
Reply With Quote
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Reply

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Manitoba & Saskatchewan
Forum Jump



Forum Jump


All times are GMT. The time now is 12:31 PM.

     
SkyscraperPage.com - Archive - Privacy Statement - Top

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.