Quote:
Originally Posted by scottN
I think it will end up as an item buried in the 2023-2025 capital plan that will be put out for voters to approve borrowing in parallel with the next civic election!in November 2022. In the last election we approved 300 million dollars of borrowing without any significant public discourse on it.
|
When the removal of the viaducts was approved in 2018, the intent was that the NEFC Public Benefits Strategy would pay the $120 million cost of replacing the viaducts with an alternate street configuration. If the viaducts were replaced with 100 year seismic structures (also $120 million) or retained but upgraded to 50 year lifespan ($90 million) then the cost would have to be covered by the Capital Plan.
In total all the costs associated with removing the viaducts, building the new roads, relocating City infrastructure and temporary traffic management was estimated at $183 miilion [page 47
here]. Another $177 million was budgeted for parks, non-City owned infrastructure work, and an $85 million contingency, putting the total budget at $360 million. Some of that has already been spent, as it includes the design and consultation for the project.
At the time it was clear that this might mean a delay in construction of the replacement, as it relies on the rezonings for the Plaza of Nations and Concord sites being enacted, and triggering the CAC payments to cover the costs. The earliest any work might start would be 2020, but realistically it's more likely to be 2021. The rezonings appear to be progressing, (although Concord might not be as keen as Canadian Metropolitan), and the City are working on the detailed designs of the various replacement elements in the meantime. Other levels of government might fund some aspects of the project.
It's been noted here that the design of the replacement bike and pedestrian structure to replace the Dunsmuir viaduct bike lanes has already had initial public consultation earlier this year. Council approved $39 million for the design and consultancies for all the North East False Creek design work, including the viaduct replacement. The 2019 City Budget showed $13.5 million expenditure this year, and the 2020 draft Budget shows a further $7.7 million next year.