Quote:
Originally Posted by necropolis
Wondering where these updates came from. The June topping out date was mentioned by the Clark Construction rep within the past couple of weeks.
Also, you said glass may be installed by June but then agreed it would be installed starting early next year. Not trying to sound argumentative but I'd like to clarify what you're saying.
|
I think I'll go with the guy ultimately responsible for getting the tower built.
As for the glass, it will begin when the garage is finished, and the tower itself starts rising. Since one or two floors will be erected before the glass, so that the glass follows the floors up, it could be earlier next year than June, but by how much I don't know.
Again, Randy Smith is saying the building will look finished from the outside by around Christmas 2018. He should know.