Quote:
Originally Posted by Skyguy_7
^I just did today. Apparently late last week they passed at 29 of 30 locations on the new system. That qualifies as passing the test, from what I’m told.
Was also told that most of the trades are submitting change orders for added work of having to come back once the curtain wall is in. The GC is backcharging the glass contractor for this. In short, it’s a disaster for them.
|
In case someone knows---I realize the GC is the big fish who is responsible for bringing the build in on time and on budget, but are individual trade contracts---such as for the glass/curtain wall--between the sub contractor and the GC or are the contracts with the owner? I am assuming that the GC can't just pick whatever subs he wants to, but who would have the final say in who got picked for the glass? That's who I think would be sweating bullets right now, especially if other trades have additional payment clauses available to them because of the glass hold up.
But maybe that's why god created lawyers.