Have started installing the 10th floor slabs on the west end now.
Reply With Quote
     
     
  #102  
Old Posted Apr 24, 2022, 3:11 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,785
Some of the 10th floor walls and posts are now up on the west side.
Reply With Quote
     
     
  #103  
Old Posted Jun 1, 2022, 5:40 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,785
Wrapping up the 10th floor walls and posts and cross beams this week. Have got a few of the roof slabs installed on the west end as well.

Last edited by jammer139; Jun 3, 2022 at 9:22 PM.
Reply With Quote
     
     
  #104  
Old Posted Jun 10, 2022, 11:52 PM
Goldenamishplumber Goldenamishplumber is offline
Registered User
 
Join Date: May 2021
Posts: 43
Was in the first building again, the second is looking real good now.
Reply With Quote
     
     
  #105  
Old Posted Jun 14, 2022, 5:15 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,785
10th floor roof slab installation is now complete. Mechanical penthouse walls should be under way this week. Still no signs they have started excavation for the underground parking for tower 3 and 4. Still using that space for worker parking. Sales for tower 3 have already started so would expect them to quickly move to that part of the site and get the excavation and footings poured before winter.



see Tricar website map - https://www.tricar.com/locations/northlink-3/
Reply With Quote
     
     
  #106  
Old Posted Jun 26, 2022, 4:15 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,785
Mechanical penthouse installation well under way now.
Reply With Quote
     
     
  #107  
Old Posted Jul 22, 2022, 8:09 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,785
Most of the external brick and stone veneer is now completed. Finishing up on the south and east side. Appears that most of the concrete crew has left and likely redeployed to Tricar's other project sites off Westdel Bourne and Westmount Estates. Would not be surprised that Tricar pauses work here at Northlink in 2023 and does not start on tower 3 construction due to the city rebuilding Sunningdale Rd between Wonderland and Richmond in 2023. They will likely have completed the apartment building on Westmount Estates and the two 4s condos off Westdel Bourne by end of 2023 and be able to return here to start tower 3 and 4. Would not be surprised they also hold off starting their 96 Ridout St project until after 2023 to allow the Ridout St bridge replacement project to complete as well.
Reply With Quote
     
     
  #108  
Old Posted Aug 25, 2022, 7:52 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,785
Excavator and dump trucks clearing the large pile of dirt where towers 3 and 4 will be. Looks like they are wrapping up the exterior brick installs now.
Reply With Quote
     
     
  #109  
Old Posted Nov 19, 2022, 3:02 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,785
Well it took a while but Tricar has finally removed the tower crane from building 2. Still finishing up the last bits of the exterior and alot of interior work is ongoing.
Reply With Quote
     
     
  #110  
Old Posted Nov 19, 2022, 11:42 PM
Goldenamishplumber Goldenamishplumber is offline
Registered User
 
Join Date: May 2021
Posts: 43
The lobby and common area furniture has been ordered, and are expecting a delivery date in January, usually happens just a few weeks before the first tenants move in.
Reply With Quote
     
     
  #111  
Old Posted Feb 12, 2023, 6:44 PM
Goldenamishplumber Goldenamishplumber is offline
Registered User
 
Join Date: May 2021
Posts: 43
Second building is pretty much finished, I units are in various stages of completion, I've got photos of the furnished lobby, common areas if anyone is interested in them as well.
Reply With Quote
     
     
  #112  
Old Posted Feb 13, 2023, 1:54 PM
MolsonExport's Avatar
MolsonExport MolsonExport is online now
The Vomit Bag.
 
Join Date: Oct 2003
Location: Otisburgh
Posts: 44,905
These look decent and pricey. Anyone know what the rent rates are? (Just curious...I am not looking to rent as I own a house in Hyde Park)
__________________
The whole problem with the world is that fools and fanatics are always so certain of themselves, and wiser people so full of doubts. (Bertrand Russell)
Reply With Quote
     
     
  #113  
Old Posted Feb 13, 2023, 11:33 PM
Djeffery Djeffery is offline
Registered User
 
Join Date: Oct 2017
Location: London
Posts: 4,534
Quote:
Originally Posted by MolsonExport View Post
These look decent and pricey. Anyone know what the rent rates are? (Just curious...I am not looking to rent as I own a house in Hyde Park)
They are actually condos, not rentals as the title says (and they aren't Sunningdale addresses either). One in the first building is listed right now for $1.068 million. Penthouse suite, 2 bed plus den, 2 bath, 1620 sq ft. Approx $1000/month in taxes and condo fees. It looks like it was for rent last summer for $4000/month

https://www.realtor.ca/real-estate/2...it-1004-london

There's also a 1 bed, 1 bath, under 1000 sq ft on the first floor listed for $579k.
Reply With Quote
     
     
  #114  
Old Posted May 18, 2023, 12:34 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,785
Looks like Tricar has applied for a building permit for building 3.


Suspect we will see the crew that did the Westmount Estate IV building return up to Sunningdale and Callaway this Fall.



https://pub-london.escribemeetings.c...cumentId=99252
Reply With Quote
     
     
End
 
 
Reply

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Ontario > London > Projects & Construction Updates
Forum Jump



Forum Jump


All times are GMT. The time now is 1:47 PM.

     
SkyscraperPage.com - Archive - Privacy Statement - Top

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.