Old Posted Aug 2, 2022, 11:33 PM
Djeffery Djeffery is online now
Registered User
 
Join Date: Oct 2017
Location: London
Posts: 4,535
Quote:
Originally Posted by jammer139 View Post
Very common indeed for high rise buildings. Very tall buildings it is common to see lower floors occupied before the concrete forming of the higher floors is even finished.
In fact, with Pomeroy, we looked at the model suites on the first floor a full year before my inlaws moved into their unit a little over midway up, and they still had several floors left to even pour.
Reply With Quote
     
     
  #102  
Old Posted Aug 25, 2022, 7:54 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,786
Tower crane has been removed from the site. Windows and balcony doors appear to now be installed.
Reply With Quote
     
     
  #103  
Old Posted Aug 28, 2022, 7:16 PM
Djeffery Djeffery is online now
Registered User
 
Join Date: Oct 2017
Location: London
Posts: 4,535
A few more floors would make this really impressive to see as you come down Wonderland at Commissioners

Reply With Quote
     
     
  #104  
Old Posted Sep 15, 2022, 5:29 PM
johnnyhamont's Avatar
johnnyhamont johnnyhamont is offline
Registered User
 
Join Date: Dec 2015
Posts: 1,115
From the contractor a couple weeks ago:









source
Reply With Quote
     
     
  #105  
Old Posted Sep 29, 2022, 9:55 PM
Goldenamishplumber Goldenamishplumber is offline
Registered User
 
Join Date: May 2021
Posts: 43
Drove by today and was able to snap a shot while waiting for the light. It's really coming together.
Reply With Quote
     
     
  #106  
Old Posted Oct 26, 2022, 7:23 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,786
Making progress with exterior concrete finishing. Would guess over 70% is now complete.
Reply With Quote
     
     
  #107  
Old Posted Dec 2, 2022, 6:24 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,786
Still working today on concrete finishing near top of this building. Appears they may already have some tenants living on the lower floors as there are patio chairs on some balconies.
Reply With Quote
     
     
  #108  
Old Posted Dec 2, 2022, 11:25 PM
Djeffery Djeffery is online now
Registered User
 
Join Date: Oct 2017
Location: London
Posts: 4,535
There's been people living in there for a couple months now. I noticed when we went to the advance poll at the arena next door before the city election that people were coming and going and the furniture on balconies.
Reply With Quote
     
     
  #109  
Old Posted Jan 21, 2023, 12:11 AM
CanadianTalk CanadianTalk is online now
Moderator
 
Join Date: Jun 2021
Location: London, Ontario
Posts: 692
In case anybody is interested in a street view, Google already went by the area last month.

https://www.google.com/maps/@42.9386...7i16384!8i8192

You can also see the almost-complete Southdale Road expansion in the street view.

Last edited by CanadianTalk; Jan 21, 2023 at 12:27 AM.
Reply With Quote
     
     
  #110  
Old Posted May 2, 2023, 3:03 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,786
They still have the exterior construction elevator setup on this building.
Reply With Quote
     
     
  #111  
Old Posted Jul 20, 2023, 2:41 AM
CanadianTalk CanadianTalk is online now
Moderator
 
Join Date: Jun 2021
Location: London, Ontario
Posts: 692
When I type in this address into the city's building permit registry, it appears that York has filed a building permit application about a month and a half ago, for two towers with heights of 22 stories and 19 stories.

My guess is that it will be the buildings proposed for right at the corner of Southdale and Bostwick, since it's marked on the master plan as 21s and 18s.

Zedd Architectures site: https://www.zeddarchitecture.com/19-028

Reply With Quote
     
     
  #112  
Old Posted Jul 20, 2023, 12:35 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,786
This is described as site 1 of the complex York plans to build in the Bostwick area. Would be interesting decision to start here rather then finish the previous site where they have switched from a 4s office building to a 11s residential building fronting on Southdale Rd. They already have the underground parking and footings built for the 11s tower and would only need to reinstall a tower crane and start forming. The site 1 corner will need them to build the access roadway that will service the entire west side of the site.
Reply With Quote
     
     
  #113  
Old Posted Jan 11, 2024, 4:03 PM
CanadianTalk CanadianTalk is online now
Moderator
 
Join Date: Jun 2021
Location: London, Ontario
Posts: 692
York has applied for a zoning change to allow for a "12-storey mixed-use apartment building containing 120 residential units and 162.5sq.m of commercial space", just north of the recently constructed 17-storey building, fronting onto Southdale.

The original plan for this spot was a commercial/office building (3 stories IIRC).

The public meeting will be on Tuesday, March 19, 2024.

Planning application page: https://london.ca/business-developme...3050-yorkville

Planning application notice: https://london.ca/sites/default/file...692-Notice.pdf

Reply With Quote
     
     
  #114  
Old Posted Jan 11, 2024, 5:37 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,786
12s is even better. They already have the foundation and underground parking built so putting the 12s on top has a head start. Would love to see them start this before they start on the other buildings on this location.
Reply With Quote
     
     
  #115  
Old Posted Mar 13, 2024, 4:56 PM
CanadianTalk CanadianTalk is online now
Moderator
 
Join Date: Jun 2021
Location: London, Ontario
Posts: 692
City planning staff is recommending that Council approve the zoning changes that would allow for the proposed 12-storey mixed-use building fronting onto Southdale, just north of the recently constructed 17-storey building.

This goes to Council's Planning and Environment committee on March 19th, then to Council on April 2nd.

https://pub-london.escribemeetings.c...umentId=107028
Reply With Quote
     
     
  #116  
Old Posted Mar 13, 2024, 8:24 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,786
Makes sense to build this before any of the other towers proposed for the site given the underground parking and footings are already in place. Would not be surprised to see this be York's next construction project after the 17s up at Wonderland and Fanshawe.



Quote:
Originally Posted by CanadianTalk View Post
City planning staff is recommending that Council approve the zoning changes that would allow for the proposed 12-storey mixed-use building fronting onto Southdale, just north of the recently constructed 17-storey building.

This goes to Council's Planning and Environment committee on March 19th, then to Council on April 2nd.

https://pub-london.escribemeetings.c...umentId=107028
Reply With Quote
     
     
  #117  
Old Posted Apr 10, 2024, 1:19 AM
CanadianTalk CanadianTalk is online now
Moderator
 
Join Date: Jun 2021
Location: London, Ontario
Posts: 692
Council approved the zoning changes for the 12-storey building.


Quote:
Originally Posted by jammer139 View Post
Makes sense to build this before any of the other towers proposed for the site given the underground parking and footings are already in place. Would not be surprised to see this be York's next construction project after the 17s up at Wonderland and Fanshawe.
It looks like York filed for another building permit for the 2 towers right at the corner of Bostwick and Southdale last month. What's strange is that they already applied in May 2023 for the same towers (which I shared on here last year). Not sure what the difference is between the two permits, but it seems like this will be York's next phase.

Reply With Quote
     
     
End
 
 
Reply

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Ontario > London > Projects & Construction Updates
Forum Jump



Forum Jump


All times are GMT. The time now is 11:35 PM.

     
SkyscraperPage.com - Archive - Privacy Statement - Top

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.