This endless saga is back in court today.

Quote:
The purpose of the case, filed by the city, is to determine whether or not the Saskatchewan Building and Accessibility Standards Board had the right to give the developer the option to continue construction. The city says the developer cannot continue with construction without applying for the proper permits.

...The matter is complicated further by the fact there is no transcript from the appeal hearing in July.

Justice Keene must now read through 1,000 pages of submissions before deciding whether or not the appeal board’s decision should be overturned.
https://regina.ctvnews.ca/judge-weig...case-1.4146303


It's sort of ridiculous there are no transcripts from the hearing where the Saskatchewan Building and Accessibility Standards Board gave the developer three options: fill the site, build permanent shoring of the excavation, or complete the project. There doesn't seem to be a timeline for the judge to rule on this.