Bringing this one back up...
I would have posted earlier about it, but I didn't realize there was a thread related to it.

This project is moving along as I put a bid in on it at the end of April. The unassuming existing building is, and stays, a 2-level parking garage with minor renovations. The apartment building is pretty simple. Foundation, 2nd level is suspended concrete, then the remaining floors are stick framing. Nothing crazy big.

Last I heard was the start of construction date (July 2018) got pushed back about a month or so. Because of this, the GC has not released contracts to subs at this point.

(...just sitting on my hands waiting.....)