Quote:
Originally Posted by cllew
I think they are back doing manual asbestos abatement in the building which has put it behind schedule. Apparently Rackowski Demo found some more asbestos in previously inaccessible areas after the first time the crews went through to remove what was known in the contract. The cost increase is still in the contingency fund range so it won't (as of the end of February) cost more than the project budget
|
Just saw this reply, thanks!