View Single Post
  #87  
Old Posted Jun 19, 2013, 6:54 PM
Sands Sands is offline
Registered User
 
Join Date: May 2013
Posts: 304
Quote:
Originally Posted by Design-mind View Post
Unfortunately they are not that quick. Once forms are up there is still a lot of work to do like measuring and placement of electrical conduit as well as plumbing. Once this is complete then comes the task of placing rebar. But hopefully next week sometime would be great.
I see. If they can do 2 and half floor per month, then they be able to top off by the end of this year.