Originally Posted by Alanky
Visited Vista site on Monday. Foreman stated they were working on a holiday because they were 10 months behind and normally they would be up to 70th floor with the glass. I spoke with someone with Magellan later in the week and was informed the glass delays will not effect the move in date of the first residents in February 2020. I was also told Wanda will definitely be the hotel operator despite not owning the building.
|
Interesting... hard to believe the developers had that much fluff in their move in schedule that they could absorb a 10 month delay. They may be trying to save face. Also, it seems like they still have some issues as they have still not completed a full floor of glass. Looks like they are skipping the east elevation balconies for some reason. Anyone know what's going on there?