Developper's news report on Zhongrong Jasper Tower (2005/09/30) :

After achieving complete success of pouring of the big bedplate and backout of the fourth strut frame in the end of June, construction of framework of third storey underground had been finished by Sep.9. Currently, the second strut frame is being removed and the framework of the second storey underground has been completed. It is believed that Zhongrong Jasper Tower, with joint efforts and meticulous organization of all the staff from each participating part, will surely be rewarded with a golden autumn of success.