Three bond packages are proposed to City Council and they will select only one for voters. I'm guessing the vote is scheduled for this fall? Two of the three bond proposals include the streetcar system. These are the bond packages proposed to City Council: A $75 million bond without the streetcar system; A $101 million bond with the streetcar system and a $125 million bond with the streetcar system. The $125 million bond also includes the city's bike lanes project. The Streetcar System's cost is set at $16,455,000 in the bonds. This is labeled as a 25% match for the first line (East-West Line from the University Medical Center to Downtown and PTRP Research Park).

Ask your councilperson and the mayor to support the $101 million bond package.